The
project is for Construction of a Waste Management Centre to the northeast of
Blandford Forum, Dorset, to provide a Household Recycling Centre and Waste
Transfer Station with access off the A350.
The current WTS in Blandford is an adapted grain store which forms part
of a combined site adjacent to the HRC. The site is small and is in poor
condition offering little scope for improvements in processing efficiency and
landfill disposal diversion. The Blandford Waste Management Centre is being
project managed by Assets and Property on behalf of Dorset Council’s waste
services.
The need for a replacement WMC in the Blandford
area was identified by Dorset Council’s Waste Services (formally the Dorset
Waste Partnership) and several sites were put forward for consideration as part
of the Bournemouth, Christchurch, Poole and Dorset Waste Plan 2019.
Cabinet
– 28 January 2025
Tender
& Procure approval – Decision
1.
That Cabinet approve the award of a contract to construct and develop a new
waste management centre at Blandford, using Dorset Highways Works Term Service
Contract within the approved capital funding.
2.
That Authority be delegated to the Executive Director for Place in consultation
with the Cabinet Member for Place Services and the Section 151 Officer to agree
the contract terms.
Decision Maker: Executive Director, Place
Decision published: 11/02/2025
Effective from: 06/02/2025
Decision:
To approve the appointment Heidelberg Materials as the main contractor
for the construction of a new Blandford Waste Management Centre.
·
For Phase 1 Highways Works
element only
Phase 2 Main Works to follow once pricing exercise has been completed.
Decision Maker: Officer Delegated Decision
Decision published: 10/02/2025
Effective from: 06/02/2025
Decision:
Decision:
Approved
Wessex Water, 06 February 2025 until 07 February 2025 –
WINTERS LANE, WADDON between the entrance to Little Waddon Vineyard and
Backwoods.
This Notice will enable Wessex Water safe access to carry
out emergency works to replace leaking tap.
Emergency works therefore no consultation carried out.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 06/02/2025
Effective from: 06/02/2025
Decision:
Decision:
Approved
Openreach 20 February 2025 between 0830 and 1530 – UNNAMED
ROAD, WYNFORD EAGLE between the entrance to Eggardon Hill Farm and Higher
Wynford Farm.
This Notice will enable Openreach safe access to carry out
pole replacement.
Consultation period: 06 January 2025 – 05 February 2025
Following consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 06/02/2025
Effective from: 27/11/2024
Decision:
Decision:
Approved
Dorset
Council 09 December 2024 until 12 December 2024 between 0900 and 1600 – B3163,
BEAMINSTER between its junction with A3066 and its junction with A356.
This
Notice will enable Dorset Council to carry out carriageway
resurfacing works and for National Grid to work in collaboration.
Consultation not carried out by Traffic Team.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 05/02/2025
Effective from: 05/02/2025
Decision:
Decision:
Approved
Dorset
Council, 17 February 2025 until 21 February 2025 – A3066, Beaminster between
its junction with Buckham Down Road and a point approximately 270 metres south
(Beaminster Tunnel).
This
Notice will enable Dorset Council to carry out carriageway maintenance.
Consultation not carried out by Traffic Team.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 05/02/2025
Effective from: 05/02/2025
Decision:
Decision:
Approved
Wessex Water 17 February 2025 until 21 February 2025 –
LONGFORD ROAD, THORNFORD between number 435 and the New House.
This Notice will enable Wessex Water safe access to carry
out a service disconnection.
Consultation period: 24 December 2024 – 02 February 2025.
Following consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 05/02/2025
Effective from: 05/02/2025
Decision:
Decision:
Approved
Dorset
Council, 19 – 21 February 2025 between 09:30 – 15:30 – B3075, Spetisbury as
indicated by signage on site.
This Notice will enable Dorset Council to carry out
carriageway maintenance and resurfacing works.
Consultation not carried out by the Traffic Team.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 04/02/2025
Effective from: 04/02/2025
Decision:
Decision:
CAMBRIDGE ROAD, WEYMOUTH - 17 February 2025 until 17 April
2025
This Notice will enable SGN to upgrade gas main.
Consultation period: 19/12/2024 - 20/01/2025
Following consultation, comments - no comments received
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 04/02/2025
Effective from: 04/02/2025
Decision:
Decision: Approved
GAS HOUSE HILL, SHERBORNE LEVEL CROSSING - 22nd February
2025 until 23rd February 2025.
This Notice will enable Network Rail Infrastructure Ltd safe
access to enable removal of level crossing so
that rails through the crossing can be replaced
Consultation period: 12th December 2024 to 23rd January
2025.
Following consultation, no comments received.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
High
Street, Swanage - 17th February 2025 until 3rd May 2025.
This
Order will provide SGN with a safe storage compound in connection with their
works scheduled
on
A351 High Street.
Consultation
period: 23rd October 2024 to 27th November 2024.
Following
consultation, no comments received.
(Decisions
included can be executive or non-executive in nature, depending on the
delegation given.
Please
state if the delegation was granted by the Cabinet or any other Committee or is
detailed within the
Scheme
of Delegation in the Council’s Constitution.)
Decision Maker: Officer Delegated Decision
Decision published: 03/02/2025
Effective from: 03/02/2025
Decision:
Decision: Approved
High Street, Swanage - 17th February 2025 until 3rd May
2025.
This Order will provide SGN with a safe storage compound in
connection with their works scheduled
on A351 High Street.
Consultation period: 23rd October 2024 to 27th November
2024.
Following consultation, no comments received.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 03/02/2025
Effective from: 03/02/2025
Decision:
Decision: Approved B3143, PIDDLETRENTHIDE - 17th February 2025 until 7th March 2025. This Order will provide Wessex Internet wth a safe working area to install fibre infrastructure. Consultation period: 1st November 2024 to 27th December 2024. Following consultation, no comments received. (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 31/01/2025
Effective from: 31/01/2025
Decision:
Decision:
WATERSTON LANE, LOWER WATERSTON - 10 February 2025 until 10 February 2025, between 09:30 and 15:30.
This Notice will enable Openreach to carry out pole testing
Consultation period: 18 December 2024 - 27 January 2025
Following consultation, comments - no comments
(Decisions included can be executive or non-executive in nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 31/01/2025
Effective from: 30/01/2025
Decision:
Decision:
Approved
Scottish and Southern Power Distribution, 13 February 2025
between 08:30 – 15:00 - Tower Hill, Iwerne Minster near Abbey Cottage.
This Notice will enable Scottish and Southern Power
Distribution safe access to replace a transformer.
Following consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 31/01/2025
Effective from: 31/01/2025
Decision:
Decision:
Approved
Openreach, 17th February 2025 and 21st February 2025 -
Station Road, Child Okeford outside Ansford Cottage.
This Notice will enable SGN safe access to carry out new
connection works.
Following consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 31/01/2025
Effective from: 31/01/2025
Decision:
Decision: Approved
Turnworth Village Road, Turnworth - 6th February 2025 until
7th February 2025.
This Notice will enable Wessex Water safe access to carry
out emergency works to repair a water main
leak.
Consultation period: N/A as urgent works.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision:
Approved
Openreach
14 February 2025 between 0830 and 1530 – UNNAMED ROAD, WYNFORD EAGLE between
the entrance to Portland Cottage and Brookside Farm.
This
Notice will enable Openreach safe access to carry out pole replacement.
Consultation
period: 23 December 2024 – 29 January 2025
Following
consultation, no comments received.
Decision Maker: Officer Delegated Decision
Decision published: 30/01/2025
Effective from: 30/01/2025
Decision:
Decision:
Approved
Openreach
14 February 2025 between 0830 and 1530 – UNNAMED ROAD, WYNFORD EAGLE between
the entrance to Portland Cottage and Brookside Farm.
This
Notice will enable Openreach safe access to carry out pole replacement.
Consultation
period: 23 December 2024 – 29 January 2025
Following
consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 30/01/2025
Effective from: 22/01/2025
Decision:
Decision:
Approved
Bridport
Market – Every Wednesday and Saturday from 05 February 2025 until 01 February
2026 between 0600 and 1700
This
Notice is to facilitate a public event on the highway.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 29/01/2025
Effective from: 29/01/2025
Decision:
Decision:
Approved
Dorset
Council, 10 February 2025 until 14 February 2025 – HERMITAGE ROAD, HERMITAGE
between its junction with A352 and Almshouse Farm.
This
Notice will enable Dorset Council to carry out surface pre-patching works.
Consultation not carried out by Traffic Team.
Lead officer: Officer Delegated Decision
To
endorse a proposal for Dorset Shared Prosperity Fund to be extended for an
additional year following government allocation of an additional £1.4 million
for FY 2025-2026.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Decision:
(a) That the Dorset Shared Property Fund Investment Plan Addendum, as attached in Appendix 1 of the report to Cabinet of 28 January 2025, be endorsed.
(b) That authority be delegated to the Executive Director for Place, in consultation with the Cabinet Member for Property, Assets and Economic Growth, to implement the Investment Plan Addendum.
Reason for the decision
To support delivery of the Council Plan priorities of
· Grow our economy
· Communities for all
· Respond to the climate and nature crisis
And to facilitate use of the funding allocated by government to benefit Dorset residents, communities and businesses.
Lead officer: Jon Bird
The
acquisition of an operating care home by Care Dorset.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Lead officer: Mark Tyson
Seeking
cabinet approval to award a contract to construct and develop a new waste
management centre at Blandford, using the Dorset Highways Works Term Service
Contract, within the approved capital funding.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 28/01/2025
Decision:
(a)
That the
award of a contract to construct and develop a new waste management centre at
Blandford, using Dorset Highways Works Term Service Contract within the
approved capital funding, be approved.
(b)
That authority
be delegated to the Executive Director for Place in consultation with the
Cabinet Member for Place Services and the Section 151 Officer to agree the
contract terms.
Reason for the
decision
To
deliver works to secure critical infrastructure in Blandford for the
development of a strategic waste transfer facility in central Dorset which will
provide the capacity to maximise the benefits of operational efficiency and
resilience to provide business continuity.
Lead officer: Gemma Clinton
This
item seeks Cabinet approval of a fee to be included in future legal agreements
to support the effective monitoring and management of planning obligations
including those relating to the delivery of infrastructure.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Decision:
(a)
That Dorset Council applies a monitoring fee
to support the cost of monitoring and reporting on planning obligations. The
fee would be based on the values and methodology outlined in the report and
applied to all planning applications submitted from the 1April 2025 which
require a planning obligation.
(b)
That following implementation, authority be
delegated to the Executive Director for Place Services and anyone nominated by
him in the scheme of nomination, to update the fee as necessary in consultation
with the Cabinet Member for Planning and Emergency Planning.
Reason for
the decision
To
enable the implementation of charges to support the staffing resource in the
monitoring and compliance of approved s106 Planning legal agreements.
Lead officer: Andrew Galpin
To
request Cabinet’s support to allocate the funding to a Registered Provider (RP)
who will use this funding along with their own resources to source 10
properties.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Decision:
(a) That £1,744,421 be granted to a Housing
Association (HA) after a competition process, who would act as the delivery vehicle
and purchase the 10 properties using these funds and their own funds. Completion
of the purchase of the properties to be finalised 31st March 2026.
(b) That a lettings plan is put in place
with the successful HA so Dorset Council can ensure the properties are
allocated in accordance with the funding requirements.
Reason for the decision
Dorset Council now owned 30 properties that were purchased with the funding granted from the Government as part of LAHF1, 26 of the properties were purchased to house Ukraine refugees and 4 of the properties were purchased to house Afghan refugees in accordance with conditions attached to the grant payment. All of these properties at some future date and on becoming vacant could be used as temporary accommodation to house those who were homeless or potentially homeless. The project was very successful however had taken a lot of resource from the Council’s Housing and Assets teams to carry out the work. Additionally, the Council was only able to grant non secure tenancies as the Council was not currently a stock holding authority. A requirement of the LAHF3 funding was that the Afghan refugees were offered secure tenancies.
To meet the short deadline, offer secure tenancies to the families from Afghanistan the properties should be provided, owned and managed by a registered provider.
Lead officer: Vikki Jeffrey
To consider the
performance report produced by Care Dorset Holdings Ltd.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 28/01/2025
Decision:
That the contents of the Care Dorset report be received and noted.
Reason for the
decision
Care Dorset was a major
delivery partner to Dorset Council for adult social care and support. Much
remained to be done to drive improvements to Care Dorset’s operation and to
grow the organisation, both in volume and revenue. The report set out the work
completed over the last 12 months to achieve Care Dorset and Dorset Council’s
shared ambitions.
To consider the
performance report produced by The Dorset Centre of Excellence.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 28/01/2025
Decision:
That the Dorset Centre of Excellence Performance report be received and noted.
Reason for the decision
To ensure Cabinet are fully informed of the current
DCOE performance.
· Full business case setting out case for change and
vision for the future with options to deliver whole council transformation.
· Final transformation plan more fully formed to
support the delivery programme for OFC and provide detail on wider service
transformation plans.
· Setting out strategic framework for transformation
for 2025-29
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Decision:
(a)
Cabinet
endorsed the overall vision and design of Our Future Council operating model
and transformation programme as detailed in the business case at Appendix A of
the report to 28 January 2025.
(b) That the proposed costs, savings and
implementation plans based on scenario 4 as set out in sections 4 and 5 of the
report and in more detail in the business case at Appendix A, sections 4 and 5,
be approved.
(c)
That
Cabinet notes that this business case was based on the proposal to transform
the organisation, implement a new operating model, and increase productivity
through the greater use of technology. The proposal identified an estimated
potential investment of £48.33M over the period 2025-28, which would release
cumulative staff savings of £77.4M over the period 2025-30.
(d) That Cabinet notes that the Our Future Council
programme would continue to be refined as we moved into the implementation
phase, but to fund the business case Cabinet agreed to:
(i)
Earmark
a further £13M in addition to the £12M already committed to the capital
programme for the Enterprise Resource Planning system. This would fund the
potential investment in technology and process change – noting that individual
funding decisions in excess of the key decision threshold would be subject to
individual business cases to be brought before Cabinet for approval.
(ii)
That Cabinet
approve the estimated redundancy costs of £9.5M over the programme, be
initially funded from reserves, noting that the reserves would need to be
replenished through budget savings over subsequent years.
(iii)
That Cabinet
approve the need for investment in internal and external additional capacity to
implement the project, to be reviewed on an annual basis, with year one of the
capacity to be funded through the approved transformation reserve of £3M and
the flexible use of capital receipts.
(iv)
That
political oversight be provided by the Members transformation steering group.
(v)
That
the recommendations from the Joint Overview Committee, set out in section 6 of
the report, be noted and the Dorset Council Transformation Plan 2025-29, be
approved, as attached at Appendix B as the framework for supporting, governing
and delivering change across the council.
Reason for the decision
The proposals outlined in the “Our Future Council Business Case and
Transformation Plan” report to Cabinet of 28 January 2025 lay the groundwork
for a comprehensive programme of transformation and improvement, enabling
Dorset Council to achieve its priorities within a sustainable medium-term
financial strategy. The ambition and commitment o
improvement and delivery as part of “Our Future Council” initiative aligned
with the Council Plan priorities and our new operating model section.
Lead officer: Nina Coakley, Lisa Cotton
To
consider the December 2024 (Quarter 3) Financial Management Report 2024/25.
Decision Maker: Cabinet
Made at meeting: 28/01/2025 - Cabinet
Decision published: 29/01/2025
Effective from: 06/02/2025
Decision:
(a) That the
Senior Leadership Team’s forecast of the full year’s outturn for the Council,
made at the end of December 2024 including progress of the transformational and
efficiency savings incorporated into the budget, be noted.
(b) That
the capital programme for 2024/25, be noted.
(c) That
the allocation of £7m from reserves to support the repairs and maintenance
compliance work of the council’s property portfolio be approved.
Reason for the
decision
The Council provided
a mix of statutory and discretionary services to communities across Dorset and
was legally required to set a balanced budget every year, and so must deliver
services within the resources made available through the revenue and capital
budgets for 2024/25.
The report
summarised the Council’s forecast financial performance for the 2024/25 year as
at the end of December 2024.
Lead officer: Sean Cremer
Decision Maker: Officer Delegated Decision
Decision published: 29/01/2025
Effective from: 29/01/2025
Decision:
Decision:
Approved
Openreach,
29 January 2025 between 0930 and 1430 – Gallows Drive, West Parley at its
junction with Christchurch Road.
This
Notice will enable Openreach safe access to carry out urgent works in the
highway to restore customer service.
Urgent
works therefore no consultation carried out.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 27/01/2025
Effective from: 24/01/2025
Decision:
Decision:
Approved
Openreach, 27 January 2025 between 0930 and 1530 – RUSHALL
LANE, CORFE MULLEN between its junction with Knoll Lane and the entrance to
Florence Cottage.
This Notice will enable Openreach safe access to carry out
urgent works in the highway to restore customer service.
Urgent works therefore no consultation carried out.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 27/01/2025
Effective from: 24/01/2025
Decision:
Decision:
Approved
Dorset Council, 26 January 2025 until 28 January 2025 –
[1] THE ESPLANADE, WEST BAY in its entirety.
[2] PIER TERRACE, WEST BAY in its entirety.
[3] BRIDPORT ARMS ROAD, WEST BAY in its entirety.
This Notice will enable Dorset Council to install flood
defence barriers.
Urgent and internal therefore no consultation carried out.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 27/01/2025
Effective from: 27/01/2025
Decision:
Decision:
Approved
Openreach, 28 January 2025 between 0930 and 1530 –
WOODLINKEN CLOSE, VERWOOD between its junction with Rowan Drive and its
junction with Woodlinken Way.
This Notice will enable Openreach safe access to carry out
urgent works in the highway to restore customer service.
Urgent works therefore no consultation carried out.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 27/01/2025
Effective from: 27/01/2025
Decision:
Decision: Approved Stapehill Road Wimborne - 27th January 2025 until 27th January 2025. This Notice is required due to health and safety reasons due to flooding. Consultation period: N/A as emergency works (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution).
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 27/01/2025
Effective from: 27/01/2025
Decision:
Decision: Approved A357 HIGH STREET, STALBRIDGE - 10th February 2025 until 14th February 2025. This Notice will provide SGN with safe access to make a new connection. Consultation period: 6th December 2024to 9th January 2025. Following consultation, no comments received. (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 24/01/2025
Effective from: 24/01/2025
Decision:
Decision: FRANCHISE STREET, WEYMOUTH - 27 January 2025 until 31 January 2025. This Notice will enable Wessex Water safe access to carry out sewer repair in the highway. Consultation period: 17/12/24 - 13/01/25 Following consultation, comments - no comments received (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 24/01/2025
Effective from: 24/01/2025
Decision:
Decision: Approved
C97, MAPPOWDER - 27th January 2025, between 09:30 and 15:30.
This Notice will enable Openreach safe access to carry out
urgent works in the highway to restore
customer service.
Consultation period: N/A as urgent works
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 24/01/2025
Effective from: 24/01/2025
Decision:
Decision:
HOLLOWAY ROAD, DORCHESTER - 7 February 2025 until 7 February
2025, between 09:30 and 15:30.
This Notice will enable Openreach safe access to telegraph
poles to provide overhead cabling.
Consultation period: 18/12/24 - 24/01/25
Following consultation, comments - no comments received
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
The
Wimborne St Giles Neighbourhood Plan 2021 to 2036 – Independent Examiner’s
Report and Progress to Referendum
Decision Maker: Cabinet Member for Planning and Emergency Planning
Decision published: 24/01/2025
Effective from: 20/01/2025
Decision:
a)
The Wimborne St Giles Neighbourhood Plan 2021 to
2036, as modified (please see Appendix B), can proceed to referendum.
b)
A recommendation to ‘make’ the Wimborne St Giles
Neighbourhood Plan 2021 to 2036 be made to a Cabinet meeting after the
referendum if the result of the referendum is in support of making the plan and
there are no other issues identified that would go against such a decision.
Wards affected: Cranborne and Alderholt;
Lead officer: Nick Cardnell
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision: Approved C94 & C21, Stalbridge - 22nd January 2025 until 23rd January 2025.
This Notice will enable Openreach safe access to carry out emergency works to replace a telegraph pole.
Consultation period: N/A as emergency works. (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision: Approved
Cheap Street, Sherborne - 19th January 2025 until 24th
January 2025, between 07:13 and 23:59.
This Notice will enable Scottish and Southern Power
Distribution safe access to carry out emergency works
to repair a cable fault.
Consultation period: NA as emergency works.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision: Approved
Smiths Lane, Piddletrenthide
- 10th February 2025 until 21st February 2025.
This Order will provide Wessex Internet with a safe working
area to undertake fibre cable installation.
Consultation period: 5th November 2024 to 31st December
2024.
Following consultation, no comments received.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision: Approved FOLKE LANE, ALWESTON - 10th February 2025 until 12th February 2025. This Notice will enable Wessex Water to Replace a Fire Hydrant Chamber. Consultation period: 31 October 2024 to 12 December 2024. Following consultation, no comments received. (Decisions included can be executive or non-executive in nature, depending on the delegation given. Please state if the delegation was granted by the Cabinet or any other Committee or is detailed within the Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision: Approved
Cauldron Crescent, Swanage - 6th February 2025 until 7th
February 2025.
This Notice will enable Wessex Water safe access to repair a
defect in the highway.
Consultation period: 5th December 2024 to 9th January 2025.
Following consultation, no comments received.
(Decisions included can be executive or non-executive in
nature, depending on the delegation given.
Please state if the delegation was granted by the Cabinet or
any other Committee or is detailed within the
Scheme of Delegation in the Council’s Constitution.)
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision:
Approved
Openreach, 19:00 on 6th February until 07:00 on 7th February
2025 - Bournemouth Road, Blandford St Mary between The Maltings and Kilderkin
Cottage.
This Notice will enable Openreach safe access to access
their overhead network in the highway.
Following consultation, no comments received.
Lead officer: Officer Delegated Decision
Decision Maker: Officer Delegated Decision
Decision published: 23/01/2025
Effective from: 23/01/2025
Decision:
Decision:
Approved
Openreach, 7 February 2025 between 09:30 – 15:30 - Various
Roads, Pamphill as listed: [i] Cowgrove Road as indicated by signage on site;
[ii] Vine Hill as indicated by signage on site.
This Notice will enable Openreach safe access to carry out
pole testing works in the highway.
Following consultation, no comments received.
Lead officer: Officer Delegated Decision