Issue details

Network Rail Infrastructure Ltd 8 May 2024 until 10 May 2024 between 2330 and 0600 – A352 at WOOL LEVEL CROSSING

Network Rail Infrastructure Ltd 8 May 2024 until 10 May 2024 between 2330 and 0600A352 at WOOL LEVEL CROSSING 

 

This Notice will enable Network Rail Infrastructure Ltd safe access to lift and replace Wool Level Crossing to carry out breather switch maintenance. 

 

Consultation period:  23 February 202422 April 2024 

 

Following consultation, no comments received 

 

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 24/04/2024

Decision due: 24 Apr 2024 by Officer Delegated Decision

Lead member: Portfolio Holder for Highways, Travel and Environment

Lead director: Executive Director, Place

Contact: Officer Delegated Decision.

Decisions