Decision Maker: Weymouth & Portland Borough Council Management Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To consider options for the improved toilet facilities in greater detail.
(a) That Option 4A as described within the report be approved and power be delegated to the Strategic Director to undertake all action including any related decisions necessary to deliver the preferred project, including the submission of any relevant planning related applications and securing all appropriate contractors;
(b) That additional funding of up to £24,000 be allocated to deliver Option 4A;
(c) That authority be delegated to the Strategic Director, in consultation with the brief holder for Community Facilities, the exact location of additional modular facilities along the seafront.
Report author: Sarah Cairns
Publication date: 15/08/2018
Date of decision: 14/08/2018
Decided at meeting: 14/08/2018 - Weymouth & Portland Borough Council Management Committee
Accompanying Documents: