Decision details

Redland Leisure and Community Park - 3G Artificial Pitches

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the release of allocated capital funds.

Decision:

(a)    That the allocation of the £689,123 be approved as a match funding contribution towards the outdoor facility improvements at Redlands Leisure and Community Park.

 

(b)    Confirmed approval for the Director Legal & Democratic Services in consultation with the Head of Assets and Property to enter into a Service Level Agreement with Active Dorset (AD) on terms to be agreed to manage the delivery of the project and compliance with the grant conditions and to sign a letter of intent and jointly with AD to enter into the works contract with FieldTurf Tarkett SAS to a contract value of up to £2,046,580.

 

Reason for the decision

 

The external facility improvements were a key part of the financial plans agreed between Dorset Council and Active Dorset when the facility was leased in November 2022.  A decision to not replace the existing pitch and build an additional 3G pitch would jeopardise the anticipated growth in income streams going forward.

 

Weymouth had higher levels of health inequalities to other areas of Dorset. A £2 million investment in recreational facilities would have a significant impact on addressing this disparity.

Report author: Paul Rutter

Publication date: 30/04/2025

Date of decision: 29/04/2025

Decided at meeting: 29/04/2025 - Cabinet

Effective from: 09/05/2025