Decision

 

(a)     That the acquisition of the land and the drainage works on the east side of Dinah's Hollow, Melbury Abbas be progressed immediately at a total cost of £130k.

 

(b)     That Cabinet notes the scale of additional resource required to stabilise slopes throughout the hollow and that the affordability of the scheme should be considered alongside other priorities as part of the 2021/22 budget setting process and MTFP.

 

Reason for Decision

The impact of a major slope failure would be high in respect of health and safety and financial implications. Possible consequences are loss of life or major injury and legal action. There would also be reputational damage, impact on service delivery and disruption to the highway network affecting a key north-south route.

 

Report author: Kate Tunks

Publication date: 09/10/2020

Date of decision: 06/10/2020

Decided at meeting: 06/10/2020 - Cabinet