Decision Maker: Officer Delegated Decision
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Wessex
Water 1 July 2024 until 12 July 2024 – St Georges Road, Portland
This
Order will enable Wessex Water safe access to install new service
Consultation
period: 23 May 2024 until 10 June 2024
Following
consultation, comments received;
Comments
were received by a resident enquiring who was benefitting from the works and
also enquired if two way access would be provided for residents.
Response
sent back to enquirer with details of the works taking place and to confirm
that two way access would be added to the Order.
Decision:
Approved
Wessex Water 1 July 2024 until 12 July 2024 – St Georges
Road, Portland
This Order will enable Wessex Water safe access
to install new service
Consultation period:
23 May 2024 until 10 June 2024
Following consultation, comments received;
Comments were received by a resident enquiring who was
benefitting from the works and also enquired if two way access would be
provided for residents.
Response sent back to enquirer with details of the works taking place and to confirm that two way access would be added to the Order.
Notice under Section 14 [2] of the Road Traffic Regulations
Act 1984 as amended.
(a) because works are being or are proposed to be executed on or near the road.
Publication date: 18/06/2024
Date of decision: 18/06/2024