Gigaclear, 13 November 2023 - 17 November 2023 - Nordon Road, Blandford Forum in its entirety.

Decision Maker: Officer Delegated Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Gigaclear, 13 November 2023 - 17 November 2023 - Nordon Road, Blandford Forum in its entirety 

 

This Notice will enable Gigaclear safe access to carry out fibre installation works in the highway. 

 

Following consultation, no comments received. 

 

Decision:

Approved to enable Gigaclear safe access to carry out fibre installation works in the highway. 

Reasons for the decision:

Notice under Section 14 [2] of the Road Traffic Regulations Act 1984 as amended. 

 

(a) because works are being or are proposed to be executed on or near the road.

 

Publication date: 30/10/2023