Decision Maker: Officer Delegated Decision
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Approved
Tilbury
Douglas on behalf of South West Water, 12 October 2026
until 30 April 2027 – JERICHO, LYME REGIS in its
entirety.
This Order
will enable Tilbury Douglas on behalf of South West
Water to carry out construction works to enlarge an existing underground screen
chamber, build a new flow control chamber, interconnecting pipework and
intersecting manholes.
Consultation
period: 21 August 2026 – 27 September 2026.
Following
consultation, comments received in regards to pedestrian
access, Tilbury Douglas advised that this will be maintained where possible but
will be times when pedestrians will be required to
follow the pedestrian diversion
Notice
under Section 14 [1] of the Road Traffic Regulations Act 1984 as amended.
(a) because
works are being or are proposed to be executed on or near the road;
None.
None.
Publication date: 30/09/2026
Date of decision: 30/09/2026