Issue - meetings

Transformation Update

Meeting: 21/04/2026 - Cabinet (Item 72)

72 Transformation Update pdf icon PDF 241 KB

To consider a report of the Cabinet Member for Corporate Development and Transformation.

Additional documents:

Decision:

(a)  That the progress to date in delivery of the 2025/26 plans including realised benefit outcomes, be noted.

 

(b)  That the 2026/27 delivery plan, including benefits, key milestones, and intended outcomes for the year be approved.

 

(c)  That the adjusted business change model for the HR, Procurement & Finance programme including the approach to resourcing, engagement, training, readiness, and adoption across all services, be agreed.

 

(d)  That Cabinet recommend to Full Council the use of up to £5.3m of flexible use of capital receipts and approve the remaining balance of £1.97m of the investment request of £7.27m be funded from reserves, for the transformation portfolio, enabling continued delivery of priority workstreams and associated benefits, including ERP – HR, Finance and Procurement system investment. To recommend approval of the updated use of flexible use of capital receipts strategy policy, summary of as set out in Appendix B of the report of 21 April 2026.

 

(e)  That the spend decision of £2.34m for digital initiatives pending final business case sign off across the next 6 months be delegated to the Chief Executive in consultation with the Section 151 officer.

 

(f)    That the updated governance and reporting cadence outlined in the report, including frequency, format, and escalation routes for programme oversight and decision making, be agreed.

 

Reason for the decision

 

The decision gave the council the direction, resources and oversight needed to deliver the 2026/27 transformation plan. They also make sure the ERP - HR, procurement and finance programme had the right support for business change. This allowed the next stage of investment to go ahead, keeps track of progress and risks, and ensure the planned benefits were achieved.

Minutes:

 

The Cabinet Member for Corporate Development and Transformation presented the report on the transitional transformation update, which set out progress since the last Cabinet report in October 2025. The report also sought approval to move to the next phase of work with details of required investment for 2026/27.

 

Cabinet noted and supported the proposal to July Full Council, as set out in appendix B, of the report regarding the approval of the updated use of flexible use of capital receipts and strategy policy.

 

It was proposed by Cllr B Wilson and seconded by Cllr S Robinson that the recommendations, which were unanimously supported.

 

Decision

 

(a)           That the progress to date in delivery of the 2025/26 plans including realised benefit outcomes, be noted.

 

(b)           That the 2026/27 delivery plan, including benefits, key milestones, and intended outcomes for the year be approved.

 

(c)           That the adjusted business change model for the HR, Procurement & Finance programme including the approach to resourcing, engagement, training, readiness, and adoption across all services, be agreed.

 

(d)           That Cabinet recommend to Full Council the use of up to £5.3m of flexible use of capital receipts and approve the remaining balance of £1.97m of the investment request of £7.27m be funded from reserves, for the transformation portfolio, enabling continued delivery of priority workstreams and associated benefits, including ERP – HR, Finance and Procurement system investment. To recommend approval of the updated use of flexible use of capital receipts strategy policy, summary of as set out in Appendix B of the report of 21 April 2026.

 

(e)           That the spend decision of £2.34m for digital initiatives pending final business case sign off across the next 6 months be delegated to the Chief Executive in consultation with the Section 151 officer.

 

(f)             That the updated governance and reporting cadence outlined in the report, including frequency, format, and escalation routes for programme oversight and decision making, be agreed.

 

Reason for the decision

 

The decision gave the council the direction, resources and oversight needed to deliver the 2026/27 transformation plan. They also make sure the ERP - HR, procurement and finance programme had the right support for business change. This allowed the next stage of investment to go ahead, keeps track of progress and risks, and ensure the planned benefits were achieved.