165 Capital funding of embankment improvements to the River Brit at West Bay PDF 78 KB
To
consider a report of the Portfolio Holders for Finance, Commercial and Assets
and Highways, Travel and Transport.
Please note that the appendix associated with this report is
an exempt document.
Decision:
Decision
(a) That the
implementation of riverbank improvements to the River Brit to commence in
October 2020, be approved;
(b) That officers
be instructed to complete an extension of the lease to the site operator of the Campfield
Holiday Park at West Bay until 31st January 2074 on terms described in the
confidential appendix which will fund the cost of the project works.
Reason for
Recommendation:
A
decision is required to progress the riverbank reinforcement project to the
River Brit in
West Bay, to address the risk of river flooding to the Campfield
Holiday Park and adjacent properties in Forty Foot Way.
The
Council is the freehold owner of the Campfield
Holiday Park which is leased to Parkdean Resorts who
have been the Council’s tenant for 53 years. Parkdean
Resorts are prepared to fund the estimated project costs from a capital premium
in return for granting a 50 year lease extension that will encourage the tenant
to continue to invest in a sustainable business in West Bay.
Minutes:
The Portfolio Holders for Finance,
Commercial & Assets and Highways, Travel & Environment set out a report
seeking authority to implement riverbank improvements to the River Brit with
the work planned to commence in October 2020. The Portfolio Holder for Finance,
Commercial and Assets advised that the funding proposal for the project
presented no significant cost to the Council whilst also producing an enhanced
annual rent payable by the tenant of good covenant. The Portfolio Holder for Highways Travel
& Environment reported that he fully supported the recommendation.
Decision
(a) That the
implementation of riverbank improvements to the River Brit to commence in
October 2020, be approved;
(b) That officers
be instructed to complete an extension of the lease to the site operator of the Campfield
Holiday Park at West Bay until 31st January 2074 on terms described in the
confidential appendix which will fund the cost of the project works.
Reason for
Recommendation:
A
decision is required to progress the riverbank reinforcement project to the
River Brit in
West Bay, to address the risk of river flooding to the Campfield
Holiday Park and adjacent properties in Forty Foot Way.
The
Council is the freehold owner of the Campfield
Holiday Park which is leased to Parkdean Resorts who
have been the Council’s tenant for 53 years. Parkdean
Resorts are prepared to fund the estimated project costs from a capital premium
in return for granting a 50 year lease extension that will encourage the tenant
to continue to invest in a sustainable business in West Bay.
33 Capital funding option for the West Bay Coastal Improvements Project PDF 115 KB
Additional documents:
Decision:
Decision
That
a decision be deferred to enable further exploration of alternative options.
Reason for decision: A deferral will provide the Council with the opportunity to explore alternative options for the funding of the improvements project.
Minutes:
The
Cabinet Member for Highways, Travel and Environment proposed that a decision on
the report to secure a capital funding contribution towards works forming part
of the current West Bay Coastal Improvements Project from the tenant of the
Council’s Campfield Site in exchange for granting a
lease extension be deferred to enable further exploration of alternative
options.
Decision
1. That a decision be deferred to enable further
exploration of alternative options.
Reasons
for Decision
A deferral will provide the
Council with the opportunity to explore alternative options for the funding of
the improvements project.