Outline Application
Develop land by the erection of 83 dwellings (48 houses and 35 apartments), new and refurbished commercial floor space, associated car parking and new vehicular and pedestrian accesses following demolition of some commercial units. Make repairs to flood wall immediately west of 'Tower Building'. Appearance and landscaping reserved for further approval. (Further revised scheme).
Attached to this report are:
Appendix 1 – 15 June 2023 Committee Report
Appendix 2 – 06 July 2017 Committee Report
Appendix 3 – 15 June 2023 Committee Update Sheet
Minutes:
The Development
Management Area Manager provided members with the following update, which
related to all applications on the agenda:
With the aid of a
visual presentation including plans and aerial photographs, the Lead Project
Officer identified the site and explained the proposal and relevant planning
policies to members. It was explained that the application was returning to the
committee for determination following suggested changes to planning conditions
in light of information published this year by the Council in respect of flood
risk.
The location of the
application site was shown to members and nearby listed buildings and
non-designated heritage assets were outlined. Photographs of the site and
surrounding area were also provided, to give members an indication of the
current condition of the site. The Lead Project Officer detailed the proposal,
which included the demolition of buildings on the site and the construction of
new buildings for commercial and residential use.
The key planning
issues were summarised for members and the Lead Project Officer explained that
the applicant had submitted a flood risk assessment to ensure the buildings
would be safe for their lifetime and several of the changed planning conditions
related to the flood risk assessment. The planning conditions were shown and
the changes to the previously approved application were highlighted.
There were no public
speakers.
In response to
questions from members the Lead Project Officer provided the following
responses:
Proposed by Cllr
O’Leary and seconded by Cllr Wheller.
Decision:
A: That authority be
delegated to the Head of Planning and the Service Manager for Development
Management and Enforcement to grant subject to the completion of a S106 Legal
Agreement with the following heads of terms:
1)
14
affordable dwellings (a minimum of 70% social / affordable rent and a maximum
of 30% intermediate affordable housing) to be provided in accordance with an
agreed Affordable Housing Scheme with the phasing of 1/D/11/002012 and
WD/D/16/002852 interlinked via a phasing plan in the Section 106 Agreement
based broadly on Phasing Plan Ref. SM1 Rev A received April 2023 and Phasing
Breakdown dated June 2022;
2)
Agreement and subsequent implementation of an
“Employment Buildings Refurbishment Scheme”, (based broadly upon Appendix C
Regeneration of Commercial Estate of the Design and Access Statement submitted
in support of the application) with the phasing of 1/D/11/002012 and
WD/D/16/002852 interlinked via a phasing plan in the Section 106 Agreement
based broadly on Phasing Plan Ref. SM1 Rev A received April 2023 and Phasing
Breakdown dated June 2022;
And subject to
planning conditions set out in the appendix to these minutes and if the revised
NPPF has been published prior to the issuing of the planning decision not to
issue the planning decision unless and until officers have agreed with the
chair of the Western and Southern Area Planning Committee that there are no
changes in the revised NPPF which could have led to members reaching a
materially different conclusion on the application.
B: That authority be
delegated to the Head of Planning and the Service Manager for Development
Management and Enforcement to refuse planning permission for the reasons set
out below if the S106 Legal Agreement is not completed by 12 June 2025 (6
months from the date of committee) or such extended time as agreed by the Head
of Planning and the Service Manager for Development Management and Enforcement:
1)
In the absence of a satisfactory completed legal
agreement to secure affordable housing and an employment buildings
refurbishment scheme, the development would be contrary to Policies HOUS1 and
BRID5 of the West Dorset, Weymouth and Portland Local Plan (2015) and Policies
H1, H2 and COB4 of the Bridport Neighbourhood Plan.
Supporting documents: