Application for Full Planning Permission
Redevelopment, including part demolition of listed and unlisted structures and refurbishment of retained structures to provide: (a) 9 residential units (including refurbishment of one existing unit); and (b) a net decrease of 47 sq. m. of light industrial floorspace.(Revised scheme)
Attached to this report are the following appendices:
Appendix 1 – 15 June 2023 Committee Report
Appendix 2 – 06 July 2017 Committee Report
Appendix 3 – 15 June 2023 Committee Update Sheet
Minutes:
With the aid of a
visual presentation including plans and aerial photographs, the Lead Project
Officer identified the site and explained the proposal and relevant planning
policies to members.
Details of the
proposed development were provided, which included the construction of 9
2-bedroom flats for residential use. There had been a slight reduction in total
floor space compared to the previous application but an improvement in the
useability of the space. The floor plans and elevations of the proposed
development were shown, to give an indication of the scale and design of the
proposed building. It was explained that the design of the proposed building
took inspiration from the existing listed buildings and non-designated heritage
assets in the area.
The key issues were
summarised and the planning conditions were shown to members, with the changes
highlighted.
There were no public
speakers.
In response to a
question from one member the Lead Project Officer explained that the viability
assessment of the site had been conducted to include both applications
together.
Proposed by Cllr
O’Leary and seconded by Cllr Wheller.
Decision:
A: That authority be
delegated to the Head of Planning and the Service Manager for Development
Management and Enforcement to grant subject to the completion of a S106 Legal
Agreement with the following heads of terms:
1)
14 affordable dwellings (a minimum of 70% social
/ affordable rent and a maximum of 30% intermediate affordable housing) to be
provided in accordance with an agreed Affordable Housing Scheme with the
phasing of 1/D/11/002012 and WD/D/16/002852 interlinked via a phasing plan in
the Section 106 Agreement based broadly on Phasing Plan Ref. SM1 Rev A received
April 2023 and Phasing Breakdown dated June 2022;
2)
Agreement and subsequent implementation of an
“Employment Buildings Refurbishment Scheme”, (based broadly upon Appendix C
Regeneration of Commercial Estate of the Design and Access Statement submitted
in support of the application) with the phasing of 1/D/11/002012 and
WD/D/16/002852 interlinked via a phasing plan in the Section 106 Agreement
based broadly on Phasing Plan Ref. SM1 Rev A received April 2023 and Phasing
Breakdown dated June 2022;
And subject to
planning conditions set out in the appendix to these minutes and if the revised
NPPF has been published prior to the issuing of the planning decision not to
issue the planning decision unless and until officers have agreed with the
chair of the Western and Southern Area Planning Committee that there are no
changes in the revised NPPF which could have led to members reaching a
materially different conclusion on the application.
B: That authority be
delegated to the Head of Planning and the Service Manager for Development
Management and Enforcement to refuse planning permission for the reasons set
out below if the S106 Legal Agreement is not completed by 12 June 2025 (6
months from the date of committee) or such extended time as agreed by the Head
of Planning and the Service Manager for Development Management and Enforcement:
1)
In the absence of a satisfactory completed legal
agreement to secure affordable housing and an employment buildings
refurbishment scheme, the development would be contrary to Policies HOUS1 and
BRID5 of the West Dorset, Weymouth and Portland Local Plan (2015) and Policies
H1, H2 and COB4 of the Bridport Neighbourhood Plan.
Supporting documents: