Application to modify legal agreement dated 18 February 2021
( PA 3/17/3609/OUT) variation of S106 to 'swap’ the
order of SANG delivery, requiring the following changes:
- Swap the references to SANG A and B on Plan 1
- Reverse references to SANG A and B in the definitions
(where there is a distinction in the wording between the two types of SANG)
- Reverse the Successors in Title paragraphs 7.3.3 and 7.3.4
- Reverse the definitions in Schedule 6 (including the
certificate/practical completion and step-in maintenance contribution
references)
- Swap S6 Parts 2 and 3 and reverse the SANG references
therein.
- Mechanism inserted to secure the 2ha of temporary
grassland is planted across the old SANG A (what will be SANG B).
Minutes:
With
the aid of a visual presentation including plans and aerial photographs, the
Lead Project Officer identified the site and explained the proposal, which was
to swap the delivery of SANG A and B that had previously been given approval.
The
planning history of the site was outlined and it was explained that the SANGs
made up part of a wider development that had been given approval and due to
changes in the construction phase of the development the applicant was
requesting to change the order of delivery of the SANGs. Photographs of the
SANG were provided, showing that it was under construction. The changes
proposed were explained to members.
The
Lead Project Officer explained that consultees, including Natural England and
the Dorset Council Heathland Mitigation team, had no objections to the
application. There had been a number of objections based on the impact on
neighbouring amenity, however it was considered that the screening capabilities
of the western SANG were limited and that the construction of the dwellings was
controlled by the approved construction management plan.
Public
representation was received in objection to the application from Mr Elliott,
Cllr Barber on behalf of West Parley Parish Council and Cllr Parry the local
Ward Member. They expressed concern that the developer was trying to maximise
profit at the expense of delivering the initially agreed scheme and that there
had been poor communication between the developer and local residents. They
also considered that the parking provision was insufficient for the site and
that access to the site would be unsafe while construction was still ongoing on
the rest of the development.
Mr
Nash spoke in support of the application, as the agent for the application. He
noted that there had been changes to the construction of the site, that
required the delivery of the SANG’s to change and that the applicant had agreed
to deliver a larger SANG area than was required for the size of the
development. He also noted the changes to the planning obligation allowed for
the occupation of the affordable housing on site, which had recently been
completed.
The
Heathland Mitigation Officer clarified that there was a two-hectare space of
grassland, which provided access to the SANG for existing residents and that it
had been agreed with the Site Manager to install signage to make it clear that
people were able to cross the site, while construction was ongoing nearby. It
was also noted that the SANGs would be maintained by the developer until they
were transferred to a management body.
In
response to members questions, the Lead Project Officer provided the following
responses.
·
The application
was to change the delivery of the SANG, so the applicant was entitled to start
construction under the previous approval.
·
Outline
permission was granted for the site under a different applicant and the current
applicant had since taken over the site.
·
Both SANGs were
secured by a S106 legal agreement, so an application would have to be brought
to committee if the applicant no longer wanted to deliver both SANGs.
·
The parking,
access and layout for the site had been agreed under the outline permission and
was not a part of the application under consideration.
Several
members expressed concern that the access to the SANG for members of the public
may be unsafe, particularly while construction was ongoing elsewhere on the
site.
The
meeting adjourned to allow officers to construct a suitable form of wording to
reflect the concern raised by members. 11:00 – 11:13
It
was proposed by Cllr Coombs and seconded by Cllr Sowry-House to Grant as per
the officer recommendation with the addition that the SANG management plan also
be required to include safe access for the public during construction of the
whole development across the 2ha SANG entrance area to the eastern SANG with
details delegated to the Head of service in consultation with the Committee
chair.
Proposed
by Cllr Coombs and seconded by Cllr Sowry-House.
Decision:
A)
That permission
be granted subject to the completion of a legal agreement under section 106 of
the Town and Country Planning Act 1990 (as amended) in a form to be agreed by
the legal services manager to amend planning conditions as follows and with the
addition that the SANG management plan also be required to include safe access
for the public during construction of the whole development across the 2ha SANG
entrance area to the eastern SANG with details delegated to the Head of service
in consultation with the Committee chair:
-
Swap the
references to SANG A and B on Plan 1.
-
Reverse
references to SANG A and B in the definitions (where there is a distinction in
the wording between the two types of SANG).
-
Reverse the
Successors in Title paragraphs 7.3.3 and 7.3.4.
-
Reverse the
definitions in Schedule 6 (including the certificate/practical completion and
step-in maintenance contribution references).
-
Swap S6 Parts 2
and 3 and reverse the SANG references therein.
-
Mechanism
inserted to secure the 2ha of temporary grassland is planted across the old
SANG A (what will be SANG B).
-
Secure delivery
of local equipped area for play (LEAP) by July 2025.
-
Amend SANG
delivery trigger to prior to the occupation of the 49th dwelling.
Or
B)
Refuse permission
if the legal agreement under section 106 of the Town and Country Planning Act
1990 (as amended) is not completed by (6 months from the date of the committee)
or such time as agreed by the Head of Planning.
Supporting documents: