Enabling residential development of 16 dwellings to facilitate restoration of listed farmhouse and mill building.
Minutes:
The Lead Project Officer presented the application,
which was for the erection of 16 dwellings to facilitate the restoration of a
Grade II farmhouse and mill. The location of the site was highlighted on a site
plan and an aerial photograph of the area. Photographs were also provided of
the site, showing the current buildings in a poor state of repair. Members were
shown photographs looking across the site, to give an indication of the
topography of the site.
It was explained that the proposal was for the
development of 16 dwellings with associated parking, to enable the restoration
of the two listed buildings. The proposed site plan and elevations of the
dwellings were shown, giving an indication of the design and scale of the
development, which would have a traditional design in keeping with the rural
setting. Members were advised of the site history and pre-application advice
that had been given in respect of the proposals.
Officers advised that the development was considered
as inappropriate in the green belt. The restoration of the mill and farmhouse weighed
in favour of the proposal. Photos of the mill and farmhouse were provided and
it was noted that several of the original features of the listed buildings were
set to be retained.
It was explained that a
planning obligation was proposed to secure a delivery plan ensuring that the
dwellings could not be occupied until the works to the listed buildings were
completed to the satisfaction of a conservation officer.
The key planning issues
were summarised. There were not considered to be harmful impacts on heritage
assets. Members were advised that the scheme represented a high quality of
design. Highways impacts were considered to be acceptable subject to conditions
to ensure safe access would be provided and retained and concerns around flood
risk had been addressed through a flood risk plan. No affordable housing
contribution was sought due to the enabling development justification for the
development. The overall planning balance was summarised and it was considered
that very special circumstances had been identified to justify inappropriate
development in the green belt.
Public representation was received in opposition to
the application from Mrs Mathers, Cllr Clews, who spoke as a representative of
Morden Parish Council and Cllr Brenton, who spoke as the Ward Member. They
raised concerns about the need for the development, the limited benefits of the
development to Morden, the self-contained nature of the proposal, the level of
traffic that would be entering and exiting the site, parking provision on the
site and the potential for flooding on the site. It was also noted that there
was a need for smaller properties in the area and this development would not
help to address the local housing needs.
Mr Parke spoke as the agent for the application,
noting the importance of restoring the listed mill and farmhouse and that the
restoration of these historic buildings met the parameters of very special
circumstances. It was explained that the cost of restoration would be
significant and that the dwellings were required to enable the restoration of
the listed buildings.
Cllr Brenton left the room at 10:59.
The Lead Project Officer addressed points made by
the public speakers. It was explained that the need for the development did not
have to be identified by the applicant, as the application was proposed on the
need for enabling development of the listed buildings. Flood risk mitigation
works were included in the proposal and addressed flooding concerns.
The Engineer explained that highways concerns had
been addressed and the applicant had submitted a transport statement and an
independent road safety audit had been carried out and determined that highways
impacts were satisfactory. Trip generation figures had been calculated using
industry standard tools and were accepted. The access would be modified to
allow larger vehicles to enter the site and the visibility splay was considered
acceptable.
In response to members questions the Lead Project
Officer, Senior Conservation Officer and Engineer provided the following
responses:
· A viability assessment had
been undertaken to determine the minimum level of development that would be
required to facilitate the restoration of the listed buildings.
· There was a difference of
approximately £1.2 million between the District Valuers appraisal and the
applicant’s appraisal and a profit margin of 17.5% was included in the final
figures.
· Affordable housing was not
being provided as to do so would result in an increase in the overall amount of
development required, but that a viability review mechanism would be included
in the proposed planning obligation agreement
· There was no proposal to
include an element of hydropower from the mill restoration as part of the
application.
· The A35 was within Dorset
Council’s responsibility and the road works included in the proposal would be
at the applicant’s expense.
· There were not concerns
about the archaeological impact of the proposal and the Archaeology Officer had
stated that the site was a sufficient distance from any sites of interest.
· Funding grants for the
restoration of the heritage assets were not considered to be sufficient to fund
the works to restore the listed buildings.
· Enabling development had
been considered on other sites within Dorset Council and predecessor authorities,
at Stapehill Abbey Parnham House.
· It was not necessary to
include additional community benefits to justify enabling development.
· It was not necessary to
provide a proof of funds for the works as the legal agreement would secure the
timely delivery of the listed building works and a draft legal agreement would
only be prepared if the committee resolved to grant permission.
· The proposed list of
conditions had not included a condition to remove permitted development rights
but that it would be reasonable to add this if members were minded to do so.
Having had the opportunity to debate the merits of
the application, several members raised concerns with the proposal. Members
considered that the proposal consisted of inappropriate development in the
green belt and that the benefit of restoring the heritage assets did not
represent very special circumstances to justify the development, which was
contrary to planning policy.
The meeting adjourned at 12:12 – 12:20.
Proposed by Cllr Ezzard and seconded by Cllr Trite.
Decision: That the application be refused for the
reasons set out in the appendix to these minutes.
Supporting documents: