Change of Use and Conversion of Four Existing Agricultural Buildings to Class C3 Residential Use Comprising 9 Dwellinghouses, Demolition of Redundant Outbuildings, Provision of Parking and Landscaping and Drainage Infrastructure.
Minutes:
The Eastern Area Team Leader, using a visual
presentation with plans and aerial photographs, identified the site and outlined
the proposal and relevant planning policies. It was noted that the site fell
outside of the Settlement Boundary and within the Cranbourne Chase National
Landscape and that such a development wouldn’t normally be permitted in an
isolated rural location, however the reuse of derelict buildings was an
exception to this policy outlined in the NPPF.
Members were shown the existing site plan and the
buildings set to be refurbished were highlighted. The proposed plans were shown
and members were provided with indicative visualisations of the appearance of
the completed development and the scale and design of the proposed dwellings,
which were considered to be in keeping with the agricultural nature of the
site. Photographs from around the site were provided, showing the current
condition of the agricultural buildings, as well as the views from beyond the
site. It was explained that concerns raised by the Parish Council that included
visibility from the access junction and flood risk to the highway had been
considered by officers but the proposals were deemed acceptable.
Mr Bennett spoke in support of the application as
the agent. He noted that the scheme would deliver a cohesive residential
community and make good use of a currently derelict site. He also noted that
the access road currently already served nearby dwellings, so it would be able
to cope with the additional road users.
The Eastern Area Team Leader and Highway Engineers
provided the following responses to members questions:
· Officers recognised that the
proposed public amenity space on the development was limited, however due to
each dwelling having its own private garden, it was considered that there was
sufficient outside space to serve the development.
· Brise-Soleil would be
installed to reduce the visibility of the glazing and reduce light spill.
· The applicant had provided a
thorough analysis of the suitability of the access lane, which conformed to the
rural roads criteria.
· All sections of the road complied
with the criteria of requiring less than 200m without a passing place.
· The roofs would be
constructed of interlocking grey tiles and a condition would require submission
of materials before approval.
· Officers would be hesitant
to introduce more formalised passing places along the access road as they would
change the character of the area, which lies within the National Landscape.
· There were 19 proposed car
parking spaces, with 6 being allocated and the rest unallocated.
· There was a proposed
condition that restricted all external lighting.
Having had the opportunity to discuss the merits of
the application several members had raised concerns they had with the
application, which included the lack of amenity space for residents, the
potential light pollution from the dwellings and the lack of access to the
surrounding countryside. Members agreed to change the wording of the condition
for external lighting to ensure it was more robust and add an informative note
to the proposal that reflected their discussion about opening access to the
surrounding fields to allow residents access to additional outside space.
It was proposed by Cllr Florek and seconded by Cllr
Morgan, that the application be granted, with a change to the wording of the
lighting condition and an informative note added.
Decision: That authority be delegated to the Service
Manager for Development Management and Enforcement and Development Management
Area Manager East to either:
A)
Grant permission subject to the completion of the legal agreement to
secure the necessary affordable housing contribution and the conditions set out
in the appendix to these minutes.
Or
B)
Refuse permission for the reasons set out in the appendix to these
minutes if the s106 agreement is not completed by 23 January 2026 or such
extended time as agreed by the Service Manager for Development Management and
Enforcement and/or the Development Management Area Manager East.
Supporting documents: