Retention of an existing well site for 10 years for oil production from the existing boreholes, Waddock Cross - 2 and Waddock Cross - 3, drilling of a sidetrack well, Waddock Cross - 4, and drilling of two boreholes, Waddock Cross - 5 and Waddock Cross - 6 for the appraisal and production of oil (Variation of condition 2 (Temporary Time Limit) and 3 (Restoration) of 6/2013/0001 in order to retain the wellsite for a further ten years).
Minutes:
The Case Officer presented the proposal using site plans, aerial photographs, and current site images, confirming that the site was not producing oil at the time. Key constraints included the proximity of Oakers Wood SSSI, ancient woodland, and listed buildings. The application sought to vary previous conditions, with the temporary duration of the permission and restoration of the site extended for a further 10 years to 2033. The site layout and phasing would be unamended, with the exception of new ecological mitigation and enhancements to be provided on-site. Relevant policies were considered, including Dorset’s Climate and Ecology Strategy and the Energising Dorset Growth Strategy, which supported the transition to green energy. While the development would have generated some greenhouse gas emissions, these were not considered significant at a county or national level. Updated ecological surveys informed mitigation and enhancement measures, including habitat features for invertebrates and reptiles.
The proposed extension until 2033 was deemed acceptable
within the transitional period towards net zero by 2050. New ecological
mitigation was explained, including a close boarded fence to mitigate against
light spill towards the adjacent SSSI that is used by bats. The fencing was
considered to preserve landscape character. Low traffic volumes, which would be
similar to the original permission, were not expected
to impact highway safety. Existing conditions were reviewed and retained to
mitigate impacts on amenity, ecology, landscape, and groundwater. A condition
relating to early cessation of hydrocarbon production operations prior to 1
June 2033 was circulated to members. The condition aimed to safeguard long-term
environmental and operational concerns. The recommendation was to grant
planning permission, subject to conditions.
Public Participation
Mr Whipple read a statement which addressed the national policy imperative to
maximise energy security and supply. He felt that the application breached
planning policy. It was noted that the site in question was an oil site, not
gas. Reference was made to the Climate Change Committee’s projections that oil
demand would decline significantly by 2050. The application was criticised for
lacking evidence of future commercial viability and for being in breach of the
local mineral strategy. Mr Whipple stated that the site should have been
restored over a decade ago and urged councillors to reject the application.
Mr May read a statement on behalf of Ms Finch. It was noted that the applicant
had acknowledged the potential for significant greenhouse gas emissions. He
highlighted the cumulative impact of such projects on climate change and
referenced recent Government guidance and academic studies from the University
of London. The statement criticised stated that the applicant has ignored the
most current climate policy positions and urged the committee to reject the
application due to its unacceptable environmental impact.
Ms Elcoate delivered a strong statement regarding the dangers of continued fossil fuel extraction, citing climate change as a global emergency and calling for local action. She stated that councillors had a responsibility to contribute positively to climate commitments by rejecting the application. She questioned the applicant’s conclusion that environmental impacts were not significant, noting that an estimated 350,000 tonnes of emissions represented a major impact. Ms Elcoate questioned whether such harm was justifiable for what she described as a marginal contribution to oil supply. She stated that Dorset’s own climate strategy was incompatible with the application and urged its refusal. Additional concerns raised included traffic movements and biodiversity impacts, with reference to widespread local opposition.
Mr Foster addressed the committee in support of the application, noting that a
comprehensive set of ecological surveys had been undertaken. He reported that
the applicant had engaged with Affpuddle and Turnerspuddle Parish Council, attending meetings and
answering questions. While consensus had not been reached, the applicant had
worked cooperatively. Mr Foster stated that the purpose of the application was
to regularise existing development and that, as of January 2025, the site had
provided an annual breakdown of oil reserves. The applicant had considered
climate impacts, and Mr Foster concluded that the proposal complied with both
national and local planning policies. He argued there were no provisions in the
relevant development policies that restricted continued production. Members
were asked to support the officer recommendation for approval, subject to
conditions.
Members questions and comments
Having had the opportunity to discuss the merits of the application and an understanding of all this entailed; having considered the officer’s report and presentation; the written; and what they had heard at the meeting, a motion to DEFER was proposed by Cllr David Taylor, and seconded by Cllr Belinda Bawden.
Decision: To defer the item to a later date to seek further detail on the scale of significance and whether it was possible to assess the proposal in relation to global carbon budgets, as well as national and local impacts.