Construction of a temporary solar farm, to include the installation of solar photovoltaic panels, with substations, inverters, perimeter fencing, landscaping and other associated works.
Minutes:
The Case Officer outlined the design evolution and summarised the proposal’s key benefits, including renewable energy generation, ecological enhancements, economic contributions, recreational opportunities, and soil and farm diversification, as well as other non-material benefits. Key planning considerations were addressed, particularly landscape and visual impacts given the site’s extensive visibility. Exceptional circumstances and the planning balance were highlighted, and the Case Officer concluded with a recommendation to refuse planning permission.
Public
Participation
Antony Warren highlighted significant changes to the original application, noting that the 44-acre site was located within an Area of Outstanding Natural Beauty, which government policy stated should be protected. He argued that the land was unsuitable for the proposed development and warned that approval could set a precedent for similar projects elsewhere. He emphasised the need to resist proposals motivated primarily by financial gain. Mr Warren also referred to the impact on neighbouring farms, including one surrounded by flower fields, and noted that the site had produced maize this year, demonstrating its agricultural importance. He concluded that the potential loss of valuable farmland and landscape character outweighed any proposed benefits.
The applicant stated that the need for the scheme was critical. He explained that only one viewpoint would experience any significant visual impact, and panoramic views would be possible from the 1.5ha picnic area. He emphasised that refusing the application would represent a missed opportunity, noting the scheme’s alignment with carbon neutral targets and the urgency of the matter. Mr Bainbridge referred to page 53 of the committee report, stating that any harms had been fully addressed, while the benefits—particularly in relation to renewable energy—were substantial. He highlighted the grid connection as an improvement to a rare asset and argued that the economic benefits should be given greater weight. He added that the proposal supported the Energising Dorset strategy, would deliver employment opportunities, and provide significant benefits for Dorset.
The Local Ward Member stated that the parish council had almost unanimously supported the application, recognising the parish’s desire to play its part in addressing the climate crisis and acknowledging the direct benefits that the proposal would bring. Cllr Eysenck noted the reality of living within a national landscape, which was subject to constant change, and observed that various features were already visible from the site. He highlighted that the parish had experienced significant flooding in recent years and referred to the National Planning Policy Framework, emphasising that great weight should be given to climate change considerations, which were often overlooked. While acknowledging that the proposal would have an impact on the national landscape, he noted the 40-year timescale and expressed hope that, within that period, alternative energy sources would become available.
Members
questions and comments
Having had the opportunity to discuss the merits of the application and an understanding of all this entailed; having considered the officer’s report and presentation; the written representatives; and what they had heard at the meeting, a motion to APPROVE the officer’s recommendation to REFUSE as recommended, was proposed by Cllr Spencer Flower, and seconded by Cllr Ridout, for the reason set out in the officer report.
Decision: To refuse for the reasons set out in Section 17 of the officer’s report.