Erection of 8no. flats (demolition of existing dwelling).
Minutes:
The Development Management Team Leader presented the
application for the demolition of an existing dwelling and the erection of
eight flats. A map of the town centre was shown with the application site and
areas of Special Character identified.
The site context was illustrated through photographs
showing the current condition of the land and surrounding area. It was
explained that the proposed flats would be positioned at a similar distance
from neighbouring properties as existing buildings. Attention was given to the
relationship with Flat No. 14, where the proposal would impact the outlook from
that property. It was considered necessary to require additional obscure
glazing to certain proposed windows, up to a height of 1.7 metres, to protect
privacy. The main impact identified would be a reduction in outlook from two
flats. A rooflight at No. 14 was also proposed, and further obscure glazing to
a height of 1.7 metres was proposed to prevent overlooking. The inclusion of a
balcony and windows was addressed, with a screening solution proposed to avoid
harmful overlooking.
Properties to the rear of the site, located on
Ringwood Road, were described as chalet bungalows. The proposed three‑storey
building was acknowledged as having the potential to create overlooking;
however, the it was advised that the separation distances were sufficient to
avoid unacceptable harm.
Flood risk was considered in light of updated
National Planning Policy Framework guidance and new data received during the
course of the application. The area was identified as having high groundwater
levels, with the potential for shallow flooding of up to approximately 10
centimetres at the rear of the site. The site was not located on a flood flow
path, and the predicted depths were considered modest. An indicative drainage
plan had been requested and provided, demonstrating that flood risk could be managed
through measures such as permeable paving. A sequential test was not considered
necessary, as sufficient mitigation had been demonstrated.
Highway safety was also assessed. The proposed
parking provision was in line with relevant guidelines. The road was described
as relatively narrow, and existing on‑street parking could result in a
single lane of traffic, which had been raised as a concern by local residents.
It was noted that congestion had occurred previously during construction works
at No. 14 due to vehicles parking on the highway. A construction traffic
management plan would therefore be required by condition. It was explained that
parking on the highway was lawful, and any restrictions, such as double yellow
lines, could be pursued separately by the Town Council if required.
In relation to habitats and biodiversity, the
proposal included provision for a bat roost within the cycle store, and
elevations showing this feature were presented. A temporary bat roost would
also be provided during the construction phase.
The development would result in a net increase of
seven dwellings, which carried significant weight given the current lack of a
five‑year housing land supply. It was also confirmed that there would be
no substantial harm arising from any departure from the Special Character Area
designation.
Public representation was received from Giles Moir,
as the agent for the application. He stated that the scheme had been designed
to reduce the bulk of the building and retain the appearance of a domestic
property. He noted that the proposal was compliant with policy and met the
minimum required separation distances to neighbouring dwellings and that the
Flood Risk Management team were satisfied that flood risk could be managed.
In response to questions from members, officers
provided the following responses:
· The proposal was considered
to meet intention of the guidance of the Special Character Area in terms of
landscaping, scale, mass and height and ecology.
· Trees were proposed to be
retained and there would be new boundary hedging included in the proposal.
· The flood risk assessment
had identified some risk of flooding on the site up to a depth of 10cm, which
the Flood Risk Engineer was satisfied could be effectively mitigated through a
drainage scheme.
· Condition 5 required
submission of a landscaping plan that would be agreed before any works above
ground level.
· All 10 parking spaces on
site would be unallocated.
· Condition 4 required a
Construction Method Statement to be submitted, that would include how all
vehicles would park, the agent expected that parking could take place of site,
although there may still be some on-road parking.
· The plot size was 0.15ha and
the amenity space would be partly private with some communal space.
· The bin store was proposed
to be located at the front of the site and the Waste team were satisfied with
this arrangement.
· The applicant had submitted
an Ecological Impact Assessment and had determined that the roof of the cycle
store would be an appropriate location for a bat roost.
· Condition 3 required the
detailed submission of a Surface Water Management Plan, which would be checked
with the Flood Risk Management Team.
· The site was located
approximately 100m from the junction with Ringwood Road and was located on a
30mph road, so there were not concerns about highways safety and if parking on
the road was causing issues, that could be explored separately.
Having had the opportunity to debate the merits of the
application members expressed that many of the concerns that had been raised
through the course of the debate had been addressed by officers.
It was proposed by Cllr Morgan and seconded by Cllr
Robinson that the application be granted.
Decision: That authority be delegated to the
Corporate Director for Planning, the Service Manager for Development Management
& Enforcement or the Eastern Area Development Management Area Manager to
A)
grant planning permission subject to conditions as set out in the
appendix to these minutes and the completion of a Section 106 Planning
Obligation under Section106 of the Town and Country Planning Act 1990 (S106
agreement) to secure New Forest Habitat Site mitigation.
Or
B)
Refuse planning permission for the reasons set out in the appendix to
these minutes if the S106 agreement is not completed by 20 November 2026 or
such extended time as agreed by the Corporate Director for Planning, the
Service Manager for Development Management and Enforcement or the Eastern Area
Development Management Area Manager. The reasons for refusal for failure to
secure the necessary obligations are set out in full in the appendix to these
minutes.