Proposed cable route in conjunction with approved solar farm developments (North Farm Solar Farm ref. P/FUL/2023/02829 and Woodlands Solar Farm ref. P/FUL/2023/03415) at Mannington, Horton.
Minutes:
With the aid of a visual presentation, including plans and
aerial photographs, the Case Officer identified the site and outlined
the proposal together with the relevant planning policies. An
update slide was presented, which included changes to conditions 3 and 12 and
the inclusion of an informative to satisfy the Cranborne Chase National
Landscape officer that previously approved landscaping needs to be adhered
to.
Members were shown the application site, its boundaries and
surrounding context, including previously approved solar farms and the
Mannington Substation to the southeast. The presentation highlighted nearby
designations, including a Site of Special Scientific Interest and the Cranborne
Chase National Landscape, together with the wider Green Belt
context.
The Case Officer explained that two potential cable routes,
extending to almost 10km, had been identified to connect the approved
solar farms to the National Grid. Approximately 83% of the route would
be located within existing highway verges, with around 17% crossing
undeveloped land. A preferred route was shown, although the final route would
be secured through planning conditions. Indicative trench details and cable
design were presented, and Members were advised that all affected land would be
reinstated following construction and this was secured by
condition.
The Committee was advised that statutory consultation
had been undertaken through site and press notices. Objections had
been received from the Horton Ward Councillor, as detailed within the officer
report.
The main planning considerations included the principle of
development, Green Belt impact, landscape and visual impact, heritage assets,
residential amenity, highways, flood risk, trees and biodiversity.
The proposal was considered acceptable in principle, having regard to the NPPF
and its role in supporting renewable energy infrastructure. As the cable would
be underground, officers considered there would be no significant harm to the character
of the area, heritage assets or openness of
the Green Belt.
Potential construction impacts relating to noise, dust and
traffic would be temporary and controlled through conditions. A Traffic
Management Plan had been submitted; no new accesses were proposed and
neither Dorset Highways nor National Highways had raised objections. Flood risk
consultees had also raised no objections, subject to conditions.
The impact on trees was considered minimal,
with appropriate tree and hedgerow protection measures proposed.
Whilst some woodland loss would occur within the Mannington Substation
SNCI, biodiversity mitigation and compensation, including new woodland
planting would be secured as part of the development.
In conclusion, the Case Officer advised that all
planning considerations had been found acceptable. The cable route would enable
previously approved solar farms to connect to the National Grid, contributing
to Dorset Council's climate objectives, without causing harm to the Green
Belt. The officer recommendation was to Grant planning permission subject to
conditions.
Public Participation
The Agent addressed the Committee and advised that
the proposed cable route was essential to the operation of the development. She
explained that the applicant had identified the most suitable route
with the least environmental impact, supported by a comprehensive Environmental
Impact Assessment, and noted that no objections had been received. The route
would follow existing hedgerows and highway verges wherever possible to minimise
impacts, with construction managed through the laying of cable in small
sections and the coordination of works to avoid overlap with other local
projects. Ms L Leyland highlighted the ecological enhancements proposed as part
of the scheme and confirmed that planning conditions would secure measures to
protect existing trees. Whilst acknowledging there would be some short-term
disruption during construction, she emphasised the urgent need for renewable
energy infrastructure and the benefits of enabling solar farm development.
Members questions and comments
Having had the opportunity to discuss the merits of the
application and an understanding of all this entailed; having considered the
officer’s report and presentation; the written representatives; and what they
had heard at the meeting, a motion to APPROVE the officer’s
recommendation to GRANT as recommended, was proposed by
Cllr Toni Coombs, and seconded by Cllr Belinda Rideout, subject
to conditions set out in the officer’s report, the updates reported to the
Committee, with the addition of informative notes drawing the developer’s
attention to the use of advanced cabling technology and to the careful
management of construction operations to minimise disruption.
Decision: To grant for the reasons set out
in Section 18 of the officer’s report, the updates reported
to the committee, with the addition of informative notes to the use of advanced
cabling technology and the careful management of construction
operations.