Agenda item

Transformation Update

To receive an update from the Executive Director for Modernisation & Customer Delivery.

Minutes:

The Director for Transformation and Customer Experience introduced the report. The Key message was that the transformation portfolio remained a high risk which was expected given the scale of change that was delivered. It was clear where those risks sit and had strengthened governance oversight and controls regarding them. The Enterprise Resource Planning system (ERP), which is our new HR, payroll and finance system, was discussed which had an update in the report regarding the approach for implementation and deployment to ensure that the project is fully aligned with the overarching transformation. This alignment is to ensure that we are designing our future ways of working to maximise benefits and make best use of the capabilities of the new solution. Going forward focus was to be given to making sure that changes were adopted successfully, employees were engaged and supported, and implementing solutions where clear and evidenced benefit was seen. The report provided assurance that the strengthening of governance improvement of prioritisation and strengthening of leadership oversight had continued.

 

A question was asked around section 11.3 of the report around more information on budgetary saving and whether there would be a net benefit to the transformation process. It was responded that in the period 4 financial management report a savings of £5.1 million was shown as being delivered 2026/27. These were assumptions that had been continually revised, and any changes had been brought into the quarter 2 report. It was confirmed that the cost of our Transformation Management Office was £5.2 million. However, confirm that this team includes functions that are essential to core business and functions funded through partnerships, and not all of the cost is directly linked to the delivery of our transformation programmes.

 

It was asked if there could be more depth around the third-party spending referenced in the report and wanted some assurance that it was being addressed. The work done on third party spending reduction was looking across the council at all the third party spend in pursuit of a £4 million savings requirement in the budget. It looked at where the council spent money on goods and services, who it was spent with, and what the opportunities for efficiency were such as contract renewals.

 

Concern was raised around the assurance of strengthened governance controls. It was commented that the transformation process had gone through a lot of transformation itself in terms of oversight, control, and risk management.

 

It was asked whether the £5.1 million of savings was actually delivered or whether it had been forecast. It was confirmed that £2.1 million had been delivered already, £1.1 million had high confidence of being realised, and the £2 million around third party spend was low confidence due to the work that had been surrounding it.

 

The agile methodology that had been adopted was questioned around whether the council had seen an increase in speed around delivering benefits because of the adopted methodology. It was explained that the purpose of approaching work in an agile way is to enable us to work within multidisciplinary teams and continually rebalance resources in accordance with priorities. There is a test and learn approach applied with every new activity to see what was working for the organisation and would amend the approaches where needed. Working in an agile way also helps to reduce risk by avoiding setting off down a long path of transformation which could not be changed should it not work.

 

Attention was given to the table of risk areas within the report as there was confusion around why many of the risks remained high. It was commented that only the governance and strategic clarity had reduced in risk to medium because of the assurance received from the South-West Audit Partnership which will be monitored. ERP delivery was to continue as a high risk due to the amount of change that needed to happen across the organisation. It was highlighted that the collateral risks of not achieving the transformation programme impact the current service and that the collateral will appear elsewhere in the council.

 

The recommendations were noted.

 

 