Installation of 40MW ground mounted photovoltaic (PV) solar development including a substation & new fencing with associated landscape mitigation & ecological/ecosystem service enhancements.
Minutes:
This application had been the subject of a site visit by the
committee on the Monday prior to the meeting which the following members
attended.
Cllrs Robin Cook, John Worth, Shane Bartlett, Dave Bolwell,
Alex Brenton, Jean Dunseith, Sherry Jespersen, Mary Penfold, Belinda Ridout and
David Tooke.
Cllr Mike Dyer did not attend the site visit,
therefore he did not take part in the debate or vote on the application.
The Senior Planning Officer presented the report which
proposed the Installation of 40MW ground mounted photovoltaic (PV) solar
development including a substation & new fencing with associated landscape
mitigation & ecological/ecosystem service enhancements. He gave an update on a typing error in
paragraphs 13.0 and 15.8 of the report.
The contribution towards AONB mitigation was to be collected over 40
years and not 20 as stated in the report
The proposed site was situated midway between Dorchester and
Wareham, North West of Winfrith Newburgh and to the west of East Knighton.
The presentation included maps and photographs of the application
site which was agricultural and mostly flat in nature,
noting the former nuclear power station Winfrith. The proposed location of the sub-station was
already screened with well established trees and
hedges.
The Access point to the site was via an existing bridleway
which would be upgraded to support traffic during construction and would remain
open during and after construction.
There were no plans to remove any of the trees or hedgerows from the
site.
It was noted that some existing watercourses on the site
were proposed to be left to ensure surface water drainage. There were a few neighbouring properties –
none of which directly abutted the site.
Committee members were advised that there was the potential
for surface water flooding on the proposed site layout plan and the number of
solar arrays had been reduced to accommodate that and therefore would not
exacerbate any existing flood issues on the site. The Lead Local Flood Authority were happy and
it was noted that the site was in Environmental Agency Flood Risk Zone 1 but
was not considered to be of particular risk of surface water flooding but
nevertheless any opportunity of surface water pooling had been removed from the
arrays.
A detailed landscaping plan would be conditioned it the
application were approved.
The Senior Planning Officer expanded on the information
relating to elevations, locations, the solar arrays and advised that the
security fencing would be set back from existing hedgerows to provide wildlife
corridors. He gave an overview of the proposed landscaping,
a more detailed landscaping plan was the subject of a planning condition.
Further tree and hedgerow planting would enhance screening and reduce visual
impact. The site was close to but not
within the Dorset Area of Natural Beauty (AONB)
Following the closing summary members were given the
opportunity to ask questions.
In response to committee member questions the Senior
Planning Officer advised that the bridleway continued to Winfrith Heath, the
first 50m would need to be a hard surface and would adhere to highway safety
and the safety of the horses, but the remainder would be of natural material
The proposal was considered acceptable in terms of
biodiversity which would ensure protection of any wildlife affected by the
proposals
The maximum export capacity of the solar arrays would be
40MW. This would allow the solar park to generate clean renewable energy for
the equivalent of approximately 14,000 homes a year, which would help with the
shortage of power in Dorset from the National Grid. This would be sufficient to make a difference
to the Dorset wide area
With regard to the preservation of the barrows Historic
England had been consulted and had discussions with the applicant and agreed a
financial contribution would be provided to facilitate the restoration and
improved interpretation of the two bowl barrows currently on the “Heritage at
Risk” register.
In relation to the fence surrounding the sub-station, the
onus would be on the developer to ensure this was vandal proof and complied
with Health and Safety standards, however the Senior Planning Officer advised
that a condition could be added to ensure the fencing used must be secure.
In response to the issue of de-commissioning, a plan was
detailed in condition 3 of the report to ensure compliance. Condition 8 entailed details of proposed finished levels or contours, the exact location of
the substation within the site, hard surfacing materials for the substation
including the colour, details of the CCTV cameras and the poles on which they
are situated including the height of the pole, materials and colour to be
approved by the Local Planning Authority.
Proposed by Cllr Belinda Ridout, seconded by Cllr
Bolwell:
Upon being put to the vote the Committee were unanimously
minded to grant the application subject to the conditions set out in the report
and the completion of a legal agreement under section 106 of the town and
country planning act 1990 (as amended)
in a form to be agreed by the legal services manager to secure financial
mitigation for two barrows on the heritage at risk register and for the AONB,
and recommended that the Service Manager for Development Management and
Enforcement determined the application accordingly.
Or
Refuse permission if the agreement is not
completed by 15th June 2022 or such extended time as agreed by the
Head of Planning.
This should include the addition condition
for fencing to be approved.
Following the “minded to” vote, the Head of Planning
confirmed that he had attended the site visit, listened to the presentation and
debate and would
take the decision in accordance with the committees minded
to decision.
Supporting documents: