Decision of the Portfolio Holder for Highways, Travel and
Environment
(a) That
Low Carbon Dorset can issue a grant award letter for £1,500,000 to the Canford Renewable Energy project that has been approved by
the Low Carbon Dorset Grants Panel and Board, given that the value is over the
£500,000 threshold for Executive Director decision, be agreed
(b) That,
following any future decision by the Low Carbon Dorset grants panel and board
to award grants over the key decision threshold of £500k, agreement to make any
such award be delegated to the Executive Director for Place after consultation
with the relevant portfolio holders. Any use of this proposed recommendation
would be exercised transparently, being publicised in advance in the forward
plan and afterwards in decision notices published on the Council’s website.
Decision
- Low Carbon Dorset Grant payments Over £500,000 - Dorset Council (wdwp.local)
Reason for the Decision:
The Low Carbon Dorset grant fund and the method by which
grants are paid out by Dorset Council and claimed back from the European
Regional Development Fund has already been agreed by the predecessor Dorset
County Council Cabinet. When the Low Carbon Dorset programme is successfully
completed it will be cost neutral to Dorset Council. However, Cabinet is
required to approve all key decisions with financial consequences of £500,000
or more.
This report was deferred.