Decision:
Approved
RMS Ltd 10 July 2024 until 15 July 2024 between 2000 and
0500 – A352, MIDDLEMARSH between its junction with B3146 and its junction with
C45.
This Order will enable RMS Ltd safe access to carry
out asphalt preservation and lining works.
Consultation period:
31 May 2024 – 16 June 2024
Following consultation, comments received in regards to the diversion route. This is longer than usual as it is not possible to use the A30 through Yeovil due to other works. The contractor decided to use a longer route via Blandford instead of replanning.