Issue - decisions

M&J Evans Construction Ltd, The works are programmed to commence in two phases: [i] from 2nd June 2025 until 26th June 2025; [ii] from 7th July 2025 until 25th July 2025 - Fair Mile Road, Bryanston at its junction with Dorchester Hill as indicated by

19/05/2025 - M&J Evans Construction Ltd, The works are programmed to commence in two phases: [i] from 2nd June 2025 until 26th June 2025; [ii] from 7th July 2025 until 25th July 2025 - Fair Mile Road, Bryanston at its junction with Dorchester Hill as indicated by

Decision: 

 

Approved 

 

M&J Evans Construction Ltd, The works are programmed to commence in two phases: [i] from 2nd June 2025 until 26th June 2025; [ii] from 7th July 2025 until 25th July 2025 - Fair Mile Road, Bryanston at its junction with Dorchester Hill as indicated by signage on site. 

 

This Order will enable M&J Evans Construction Ltd to carry out footway and carriageway alteration and development works. 

 

Following consultation, no comments received.