The
Executive Director for Place approved the appointment Heidelberg Materials as
the main contractor for
the
construction of a new Blandford Waste Management Centre.
· For
Phase 1 Highways Works element only (Signed off 6/2/25)
·
Phase 2 Main Works to follow once pricing exercise has been completed (12/5/25)
Revision 2 of this delegated decision covers the formal decision to commence the Phase 2 works following a formal evaluation of the confirmed contracted costs, that were not available at the commencement of the Phase 1 decision stage.