Deferred from 22 June 2021
To agree that the Low Carbon Dorset project can make payment
of a grant totalling £1,500,000 to
Canford Renewable Energy IF the application from the said applicant is approved
by the Low Carbon Dorset Grant Panel and Low Carbon Dorset Board on 23rd
June and 24th June respectively.
Decision type: Key
Decision status: For Determination
Notice of proposed decision first published: 08/06/2021
This decision will be taken under urgency procedures.
Reason for urgency:
This item ais urgent and it is considered impractical to defer making the necessary decisions until they have been included in the next Forward Plan.
Decision due: 27 Jul 2021 by Cabinet
Lead member: Portfolio Holder for Highways, Travel and Environment
Lead director: Executive Director, Place
Contact: Heather Kiel, Programme Manager - Low Carbon Dorset Email: Heather.kiel@dorsetcouncil.gov.uk.