Reason(s) for Decisions:
The
Weymouth Quay Regeneration project has been delayed over the last 4 years for a number of reasons including the covid pandemic, but also the
resulting insolvency of the main contractor who had been selected to carry out
the work. Inflationary increases in materials and fluctuating costs have made
it difficult for contractors to quote for the work, but we are now able to go
into contract with Knights Brown to deliver the long overdue quayside work. The
improvements that are to be made to the quayside will improve the public realm
and provide support to harbour users and commercial fishermen with the
intention of sustaining and creating employment and supporting Dorset Council’s
corporate priorities. The improvements will also generate additional income for
the harbour and improve harbour facilities.
Do
nothing, return the funding to DLHUC and delay the
works.
Any conflict of interest
declared by any member consulted: None
Any dispensation granted in
respect of any declared conflict of interest: N/A
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 24/08/2023
Decision due: 24 Aug 2023 by Executive Director, Place
Lead member: Portfolio Holder for Assets and Property
Lead director: Executive Director, Place
Contact: Ken Buchan, Head of Environment and Wellbeing Email: [email protected].